This memorandum provides a status report on the Shoreline Levee and Sea Level Rise Project, which aims to reduce flood risk and restore the shoreline in the South San Francisco Bay. The project is managed by the US Army Corps of Engineers in partnership with local agencies. Construction for the initial reaches is nearing completion, while design work for later reaches was paused due to cost overruns. Recent funding has allowed design work to resume, and negotiations are ongoing for land transfers necessary for project completion.
Key points
The Shoreline Levee Project aims to provide flood risk reduction and shoreline restoration.
The project is managed by the US Army Corps of Engineers with local partnerships.
Construction for Reaches 1-3 is nearing completion, expected to finish in 2025.
Design work for Reaches 4 and 5 was paused due to cost overruns but has resumed following additional funding.
Negotiations are ongoing for land transfers required for the project.
Limitations
The document contains unresolved placeholders and missing information regarding specific dates and financial details.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.
Extracted text preview · 9,176 chars
T&E AGENDA ITEM: TO: TRANSPORTATION AND ENVIRONMENT COMMITTEE SUBJECT: See Below Approved 4/7/25 (d) 5 FROM: Nanci Klein Jeff Provenzano DATE: March 17, 2025 Date: 3/27/2025 SUBJECT: Shoreline Levee and Sea Level Rise Status Report RECOMMENDATION Accept a status report on the Shoreline Levee and Sea Level Rise. BACKGROUND The South San Francisco Bay Shoreline Phase I Project (Project) is a multi-benefit shoreline levee project to provide flood risk reduction and shoreline restoration. The Project is managed by the United States Army Corps of Engineers (USACE) in partnership with the Santa Clara Valley Water District (Valley Water) as the local sponsor, and the California State Coastal Conservancy. The Project was initiated to provide 100-year coastal flood risk management, inclusive of sea level rise, to protect the community of Alviso, parts of North San José, and critical infrastructure such as the San José-Santa Clara Regional Wastewater Facility (RWF). The Project will also restore roughly 2,900 acres of former salt ponds into tidal marsh and improve public access along the shoreline via inclusion of a segment of the San Francisco Bay Trail. The RWF owns the lands that the...
Official source link unavailable.
The file was imported, but the current source metadata does not include a public document URL.
Generated summaryAI-assisted
The source text indicates this attachment appears to be a draft document.
The document is a status report on the Shoreline Levee and Sea Level Rise project, managed by the United States Army Corps of Engineers (USACE) with local sponsorship from the Santa Clara Valley Water District. The project aims to provide coastal flood risk management and restore habitat. Work was paused in September 2021 due to cost escalations, but additional federal funding was secured in February 2023, and a value-engineering exercise is underway. A non-binding Letter of Intent has been executed between the City and Valley Water, with plans for a binding MOU to be presented for approval. Key terms of the MOU include fair market value land transactions and ensuring no liabilities for the Regional Wastewater Facility. Land transfer is anticipated in summer 2026.
Key points
The project provides 100-year coastal flood risk management for Alviso and parts of North San José.
It restores approximately 2,900 acres of former salt pond to tidal marsh habitat.
USACE paused work in September 2021 due to projected cost escalations.
The City secured $91M in additional federal funds in February 2023.
A value-engineering exercise is being performed to reduce project costs.
A non-binding Letter of Intent has been executed between the City and Valley Water.
A binding MOU is being prepared and will require approval from various committees and councils.
Land transfer is anticipated after the USACE-Valley Water Design & Construction Agreement in summer 2026.
Limitations
The document appears to be a draft as it includes placeholders and lacks finalized details.
There are unresolved placeholders regarding specific dates and approvals.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.
Extracted text preview · 2,536 chars
(D) 5. Shoreline Levee and Sea Level Rise Status Report Transportation & Environment Committee April 7, 2025 Environmental Services Jeff Provenzano Director OEDCA Kevin Ice Director of Real Estate Background • South San Francisco Bay Shoreline Project – Provides 100-year coastal flood risk management for Alviso, parts of North San José, and critical infrastructure. – Restores ~2,900 acres of former salt pond to tidal mash habitat. – Provides connection for the Bay Trail. • Project managed by United States Army Corps of Engineers (USACE) as Project Sponsor – Santa Clara Valley Water District (Valley Water) is local non-federal sponsor. – CA State Coastal Conservancy is a sponsor, managing the project’s habitat restoration aspects. • Regional Wastewater Facility owns land that the Project must acquire – Staff have been collaborating with the project sponsors and engaged in the process since inception. 2 Background • USACE paused work on project in September 2021 due to projected cost escalations • The City lobbied with Valley Water and partners to secure $91M in additional federal funds in February 2023. • USACE performing a value-engineering exercise to reduce the cost of the...