This memorandum provides a status report on the Anderson Dam Seismic Retrofit Project (ADSRP), the Coyote Creek Flood Protection Project (CCFPP), and collaborative encampment outreach and cleanup efforts. The ADSRP is in final design, with construction scheduled to begin in 2027, aimed at restoring reservoir capacity and meeting safety standards. The CCFPP has completed phase one, with phase two set to start in 2026. The memorandum also details efforts to relocate unsheltered individuals from construction zones and establish No Encampment Zones along Coyote Creek.
Key points
The Anderson Dam Seismic Retrofit Project (ADSRP) is currently in final design, with construction expected to begin in 2027.
The Coyote Creek Flood Protection Project (CCFPP) has completed phase one, with phase two scheduled to start in 2026.
Collaborative outreach and cleanup efforts have relocated unsheltered individuals from project areas, with 120 individuals moving into shelter.
No Encampment Zones have been established along Coyote Creek to prevent new encampments and ensure environmental compliance.
The Valley Water Board certified the final Environmental Impact Report for ADSRP on February 25, 2025.
Limitations
The document contains placeholders and unresolved sections, such as specific dates and details about the No Encampment Zones map.
The text appears to be a draft, as indicated by the presence of 'Approved' and 'Date:' fields without filled-in values.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.
Extracted text preview · 17,036 chars
JOINT CC/VW AGENDA: FILE: ITEM: TO: HONORABLE MAYOR AND CITY COUNCIL SUBJECT: See Below Approved 8/19/25 25-820 6.1 FROM: Jon Cicirelli DATE: July 28, 2025 Date: 8/4/25 COUNCIL DISTRICT: Citywide SUBJECT: Status Report on the Anderson Dam Seismic Retrofit Project, Coyote Creek Flood Protection Project, and Collaborative Encampment Outreach and Cleanup RECOMMENDATION Valley Water District Board and the City of San José Mayor and City Council receive the status report on the Anderson Dam Seismic Retrofit Project, Coyote Creek Flood Protection Project, and collaborative encampment outreach and cleanup. SUMMARY AND OUTCOME This memorandum is focused on the Anderson Dam Seismic Retrofit Project (ADSRP) and associated Coyote Creek Flood Protection Project (CCFPP) efforts, major infrastructure initiatives led by the Santa Clara Valley Water District (Valley Water) and the City of San José (City) to address seismic safety concerns and flood risks. The ADSRP, currently in final design with construction set to begin in 2027, will restore full reservoir capacity and meet state and federal safety standards. The Anderson Dam Tunnel Project precedes this, is currently underway and near...
Official source link unavailable.
The file was imported, but the current source metadata does not include a public document URL.
Generated summaryAI-assisted
The document appears to be a presentation regarding the Anderson Dam Seismic Retrofit Project and the Coyote Creek Flood Protection Project, discussed during a joint meeting between the Santa Clara Valley Water District and the San José City Council. It includes updates on project progress, construction schedules, and encampment outreach efforts. Key personnel mentioned include Ryan McCarter and Olympia Williams.
Key points
Joint meeting held on August 19, 2025.
Projects discussed include the Anderson Dam Seismic Retrofit and Coyote Creek Flood Protection.
Construction updates provided for both projects.
Encampment outreach and cleanup efforts were also highlighted.
Key personnel involved: Ryan McCarter and Olympia Williams.
Limitations
Specific dates for project milestones are mentioned but not fully detailed.
Some sections contain unresolved placeholders and missing information.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.
Extracted text preview · 3,519 chars
Santa Clara Valley Water District & San José City Council Joint Meeting August 19, 2025 San José City Hall / Santa Clara Valley Water Headquarters Building Ryan McCarter, P.E. Deputy Operating Officer - Santa Clara Valley Water District Olympia Williams, Deputy Director – Parks, Recreation and Neighborhood Services, City of San José Anderson Dam Seismic Retrofit Project & Coyote Creek Flood Protection Project 1 v a l l e y w a t e r. o r g Update on the Anderson Dam Seismic Retrofit Project, Coyote Creek Flood Protection Project, and Collaborative Encampment Outreach and Cleanup v a l l e y w a t e r. o r g 2 Anderson Dam Seismic Retrofit Project & Coyote Creek Flood Protection Project Anderson Dam Seismic Retrofit Project Coyote Creek North Channel Unlined Spillway Extension of concrete over currently unlined channel 3 v a l l e y w a t e r. o r g South Channel Hydroelectric Facility to be disconnected and decommissioned Basalt Hill Borrow Area Existing stockpile and future borrow area Anderson Dam Tunnel Project – in construction Outlet Structure HLOW Drop Shaft Tunnel Micro-Tunnel Boring Machine (MTBM) Lake Tap v a l l e y w a t e r. o r g North Channel Weir 4 Diversion...