Memorandum
Official source link unavailable. The file was imported, but the current source metadata does not include a public document URL.
This memorandum reports on the bids and recommends awarding a contract for the construction of the 10107 – McLaughlin Avenue-24th Street Sanitary Sewer Improvement Project to C2R Engineering, Inc. The project aims to improve sewer capacity in accordance with the City of San José’s 2040 General Plan. The total contract amount is $2,338,470, with a 10% contingency of $233,847. Construction is scheduled to begin in July 2025 and be substantially completed by February 2026.
Key points
- The project involves upsizing approximately 2,200 linear feet of existing 15-inch diameter sanitary sewer main to 18-inch diameter.
- Eight new manholes will be constructed, and approximately 34 laterals will be cleaned, inspected, and reconnected.
- Bids were opened on February 27, 2025, with C2R Engineering, Inc. being the lowest responsive bidder.
- The project is exempt from CEQA requirements under Section 15301(b) for existing facilities.
- The project will not have significant adverse impacts on the operating budget.
Limitations
- The text includes unresolved placeholders such as 'Date:' and 'ITEM:' which affect the completeness of the summary.
- The document does not provide specific details on public outreach or commission recommendations.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.