Memorandum
Official source link unavailable. The file was imported, but the current source metadata does not include a public document URL.
This memorandum discusses the third amendment to the Consultant Agreement with DKS Associates for the Bascom Avenue Highway-Rail Traffic Signal Project. It recommends authorizing the City Manager to negotiate and execute the amendment, which includes increasing the maximum compensation and extending the contract term. The amendment aims to provide additional construction support for the traffic signal project, which is intended to mitigate collision risks at a busy rail crossing.
Key points
- The memorandum is addressed to the Mayor and City Council.
- The subject is the Third Amendment to the Consultant Agreement with DKS Associates.
- The recommendation includes increasing compensation by $74,768 and extending the contract term to December 31, 2027.
- The project aims to install a traffic signal at the Bascom Avenue and Vasona rail corridor crossing.
- DKS Associates was initially contracted in June 2022 and has undergone two previous amendments.
- Construction support tasks include attending meetings, preparing plan revisions, and assisting with project close-out activities.
- The funding source for the contract is the Building and Structure Construction Tax Fund.
Limitations
- The text contains unresolved placeholders such as the amount of the original contract and specific dates.
- The document does not specify the final vote or outcome of the recommendations.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.