This memorandum outlines the report on bids and the award of a contract for the 10505 – Sanitary Sewer Repairs Fiscal Year 2024-2025 Package VI Project. The contract is recommended to be awarded to SubTerra Construction, Inc. for $1,338,796, with a 10% contingency of $133,880. The project aims to repair and rehabilitate sanitary sewer segments to prevent wastewater leakage, as part of the Exfiltration Abatement Program. Construction is scheduled to begin in September 2025 and is expected to be substantially completed by January 2026. The project has been coordinated with relevant city departments and is exempt from environmental review under CEQA guidelines.
Key points
- The contract is for the 10505 – Sanitary Sewer Repairs Fiscal Year 2024-2025 Package VI Project.
- SubTerra Construction, Inc. is the lowest responsive bidder at $1,338,796.
- A 10% contingency of $133,880 is recommended for unanticipated work.
- The project will minimize the risk of wastewater leakage into storm sewer pipes.
- Construction is set to begin in September 2025 and expected to be completed by January 2026.
- The project is exempt from environmental review under CEQA guidelines.
Limitations
- The document contains unresolved placeholders and blank fields.
- The text indicates a future construction schedule but does not provide specific dates for all actions.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.