This memorandum discusses the report on bids and the award of a contract for the 10638 – 2026 Major Streets Resurfacing #2 Project. The contract is recommended to be awarded to MCK Services, Inc. for the construction of the project, which aims to resurface approximately 13 miles of streets in poor to failed condition. The total project cost is estimated at $9,956,024.26, which includes a 10% contingency. Construction is scheduled to begin in August 2026 and is expected to be substantially completed by October 2026.
Key points
- The project will resurface approximately 13 miles of streets along the Major Streets Network.
- MCK Services, Inc. is the lowest responsive bidder with a bid amount of $7,855,476.60.
- A 10% contingency of $785,548 is recommended for the project.
- The project is part of the Department of Transportation's efforts to maintain approximately 201 miles of roadway.
- Construction is scheduled to begin in August 2026 with substantial completion expected in October 2026.
Limitations
- The document contains unresolved placeholders such as specific dates and budget references.
- The attachment includes a list of streets but does not provide complete details for all entries.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.