This memorandum reports on the bids and recommends the award of a contract for the 10424 – Sanitary Sewer Repairs FY 2024-2025 Package II Project to C2R Engineering, Inc. The project aims to minimize wastewater leakage from sanitary sewer pipes into storm sewer pipes as part of the Exfiltration Abatement Program. The total contract amount is $1,467,810 with a 10% contingency of $146,781. The project includes video inspections, point repairs, and installation of cured-in-place pipe liners, with construction scheduled to begin in October 2025 and substantial completion expected by February 2026.
Key points
- The project is part of the Exfiltration Abatement Program to prevent wastewater leakage.
- C2R Engineering, Inc. is the lowest responsive bidder at $1,467,810.
- A 10% contingency of $146,781 is recommended for unanticipated work.
- Construction will involve video inspections, point repairs, and installation of approximately 7,800 linear feet of cured-in-place pipe liner.
- The project is scheduled to begin in October 2025 and be substantially completed by February 2026.
Limitations
- The document contains unresolved placeholders and blank fields.
- The text indicates a draft status but does not explicitly confirm it.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.