Memorandum
Official source link unavailable. The file was imported, but the current source metadata does not include a public document URL.
The source text indicates this attachment appears to be a draft document.
This memorandum discusses the bids and the recommendation to award a contract for the construction of the 10294 - Southwest Expressway Sanitary Sewer Improvement Project to Koios Engineering, Inc. The project aims to enhance the sewer system's capacity by upsizing existing sewer mains and installing new ones. The total contract amount is $4,420,145, with a 10% contingency of $442,014. The project is scheduled to begin construction in January 2026 and aims for substantial completion by September 2026.
Key points
- The contract is recommended to be awarded to Koios Engineering, Inc. for $4,420,145.
- A 10% contingency of $442,014 is also recommended.
- The project will upgrade approximately 800 linear feet of existing sewer main and install 4,200 linear feet of new sewer main.
- Construction is set to start in January 2026 and be substantially completed by September 2026.
- The project is part of the Sanitary Sewer Master Plan Phase III to accommodate future sewer flow demands.
Limitations
- The document contains unresolved placeholders and blank fields.
- The document appears to be a draft, as indicated by the presence of 'DRAFT' in the text.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.