Memorandum
Official source link unavailable. The file was imported, but the current source metadata does not include a public document URL.
The memorandum discusses the 10623 – 2026 Major Streets Remove and Replace Pavement Project, which involves the removal and replacement of failed pavement on approximately 26 miles of streets in San José. The contract is recommended to be awarded to O’Grady Paving, Inc. for $1,110,540, with a 10% contingency of $111,054. The project aims to improve roadway conditions and is scheduled to begin in May 2026, with substantial completion expected in July 2026.
Key points
- The project will address approximately 26 miles of failed pavement along the Major Street Network.
- The contract is recommended to be awarded to O’Grady Paving, Inc. for $1,110,540.
- A 10% contingency of $111,054 is also recommended.
- Construction is scheduled to begin in May 2026 and expected to be substantially completed by July 2026.
- The project will maintain streets designated as Equity Priority Communities.
Limitations
- The list of streets to be maintained is included as an attachment but is not fully detailed in the summary.
- The document contains placeholders and unfilled fields that affect the completeness of the summary.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.