Memorandum
Official source link unavailable. The file was imported, but the current source metadata does not include a public document URL.
The source text indicates this attachment appears to be a draft document.
This memorandum addresses actions related to the 9151 - Police Department Air Support Unit Hangar Relocation Project, recommending an increase in the construction contingency from 10% to 14% and amendments to the 2025-2026 Appropriation Ordinance. The increase in contingency is necessary to incorporate a fire foam suppression system due to changes in the hangar's use. The project is currently 75% complete, with an expected completion date of September 2025.
Key points
- The construction contingency is proposed to increase from 10% to 14%, amounting to an additional $495,000.
- The project is funded through the Public Safety and Infrastructure Bond, with a total project cost of approximately $18.86 million.
- The project includes construction of a new facility to replace existing hangars and will incorporate a fire foam suppression system.
- Construction began on January 16, 2024, and is expected to be completed by September 2025.
- The City Council awarded the construction contract to D.L. Falk Construction, Inc. for $12,660,000.
Limitations
- The document contains unresolved placeholders such as the council agenda type and specific budget action details.
- The text appears to be a draft as it includes instructions and formatting not typical of final documents.
Generated for convenience from extracted text using AI. Review the official source document before relying on this summary.